Here two cases scenario can be seen which will be treated in a different way:
- Period of non-work
Inability to install asphalt or landscaping during winter for example.
To allow this constraint to be reflected in the Ms Projet software, the easiest method will be to create a specific calendar (for example a calendar where no work is done during the winter) which will be assigned to the activities that cannot be done during the winter.
- Compulsory work period
Obligation to do work for a specified period.
To reflect and control a specific time period where we need to work, we can use a constraint (milestone) and due date on the activity or final activity of a block.