The Construction add-in allows you to manage your shop drawings with the Shop Drawings view, you can access it by changing the view or using the  View button  in the Shop Drawings group in the Construction tab.

This view allows managing the reception of the drawings using the first column Monitorer which tells us if the drawing should be watched closely because there is no delay between the Required Delivery and the Possible Delivery.

  • Fabrication float (fabrication total slack) is zero.
  • Fabrication float (fabrication total slack) have a positive float 

 

The Status Indicator field show you if

  • the drawing has been delivered 
  • the drawing was refused 
  • The drawing has been approved and is now in the manufacturing/delivery Process 
  • Is in the General constructor office 
  • Is overdue from the subcontractor or from the consultant 
  • Will be due within 5 days from the subcontractor or the consultant 
  • Or has still more than 5 days before it should be received 

 

For the shop drawing delay indicator which is by default 5 days, the value could be changed under the Construction tab, in the Tools Group sith the Settings button.

 

You also have the possibility to manage the shop drawing with the Manage Procurement View as shown below:

 

 

With the Construction add-in, in the Shop Drawings group, you can add a New Drawing , Delete a Drawing , or create a Revised Drawing . You may see more detailed instructions by clicking on the hypertext link.