If during the follow-up of the shop drawings, a drawing needs to be resubmitted, select it and click on the Revised drawing button to create a new drawing with the note rev.1, 2 or 3 as appropriate.
Fill in the required information.
Click on OK.
If the sum of both preparation and approval is delaying the project, the construction add-in will warn you.
If you say Yes, you will be able to chance the duration of the preparation or approval.
If you say No, the revised shop drawing task will be added with the link to the construction task that will cause a delay to your project.
Links to the construction task(s) in the schedule are automatically created using those in the original drawing.
In the Shop Drawings view you will have a revised drawing below the original drawing that was rejected.