When you click on the Register Progress button, the following window appears:
You must indicate the site status date and select how many weeks later you want to see.
In principle, the status date, as well as the number of weeks after this date, should correspond to the dates chosen when the Site report was displayed and sent to the superintendent.
The following display will appear:
The following display view will allow you to enter your actual dates in the Started On and Terminated On fields.
You will enter your forecasts in the Expected Start and Expected Finish fields
Please note that the File that is open as the status date in its name:
Before leaving this display, you must absolutely use the Save update or Cancel update
buttons.
The file will be saved under the same directory folder under the updated schedule folder with the status date inscribed.