This button creates an Excel sheet that will contain all the information required to establish a list of workshop drawings.
Normally, the sheet will be saved in the same directory as your schedule.
If you already have the list of drawings on an Excel sheet, you will need to copy this list to this new sheet.
You must then open the Excel software and open the file saved by our Construction Add-in.
Go to column A You must complete each column:
Excel Column title |
Description |
specification Group | Mandatory |
Drawing(s) number(s) |
Optional
|
Name |
Mandatory
|
Shop Drawings |
If required:
|
Samples |
If required:
|
Spec sheets |
If required:
|
Sub Contractor |
Mandatory
|
Preparation duration in working days |
Mandatory
|
To be approved by |
Mandatory
|
Delivery time in working days |
Mandatory
|
N.B. Do not leave empty lines; the procedure considers that the list of drawings is complete at the first empty line it encounters.
The Excel table should look like the image below.